Installation Guide

Machine Foundation Isolation Regupol® vibration

Machine Foundation Isolation with Regupol BA – Step 1
Step 1: Installing the Regupol® vibration isolation
Machine Foundation Isolation with Regupol BA – Step 2
Step 2: Exact cut to the dimensions of the foundation
Machine Foundation Isolation with Regupol BA – Step 3
Step 3: Setting up the formwork of the machine foundation
Machine Foundation Isolation with Regupol BA – Step 4
Step 4: Putting in a PE foil with a minimum thickness of 0.2 mm
Machine Foundation Isolation with Regupol BA – Step 5
Step 5: Filling with concrete
Machine Foundation Isolation with Regupol BA – Step 6
Step 6: Putting in the foundation reinforcement
Machine Foundation Isolation with Regupol BA – Step 7
Step 7: Backfilling the remaining space with concrete and smoothing everything at the end
Machine Foundation Isolation with Regupol BA – Step 8
Step 8: Allow to harden, then remove the formwork